Title
Addendum No. 12 to Regional Water Quality Control Plant Basic Agreement
Recommended Action
1. Authorize the City Manager or designee to execute Addendum No. 12 to the Basic Agreement between the cities of Palo Alto, Mountain View, and Los Altos for the City of Palo Alto to construct the Joint Intercepting Sewer Rehabilitation Phase 1 Project at the Regional Water Quality Control Plant with a cost-share not-to-exceed amount of $5,159,619 from the City of Mountain View.
2. Appropriate $235,500 in the Public Works Department in the Wastewater Fund for the Joint Intercepting Sewer Rehabilitation Phase I Project. (Five votes required)