Title
Gateway Master Plan Scope of Work
Recommended Action
1. Approve the proposed scope of work for a City-initiated Gateway Master Plan project.
2. Approve a midyear capital improvement project, Gateway Master Plan, and transfer and appropriate $535,000 from the Shoreline Regional Park Community Fund to the new project. (Five votes required)
3. Authorize the City Manager to enter into a contract with Raimi + Associates for an amount not to exceed $500,000 for the Gateway Master Plan project.
4. Transfer and appropriate $170,000 from the Shoreline Regional Park Community Fund to the North Bayshore Circulation Feasibility Study, Project 19-54, to support the Gateway Master Plan project for a new total of $1,270,000.
5. Authorize the City Manager to execute an amendment to increase the professional services agreement with TJKM Transportation Consultants for the North Bayshore Circulation Feasibility Study, Project 19-54, from $935,000 to $1,070,000 contract with TJKM to add $135,000 for the additional scope of work.