Title
Rengstorff Avenue Grade Separation, Design and Right-of Way, Project 22-27 - Cost Reduction Measures
Recommended Action
Approve the recommended cost-reduction measures for Rengstorff Avenue Grade Separation, Design and Right of Way, Project 22-27, reducing total costs by approximately ----$58.1 million through construction methods, modification and elimination of non-roadway elements, and reduced construction duration, without changing the alignment and intent of the project. Approximately 6% of the total costs from preliminary engineering through construction for the Rengstorff Grade Separation Project will be funded by the Shoreline Regional Park Community Fund.