Title
Appropriations for Advanced Planning Capital Improvement Projects
Recommended Action
1. Transfer and appropriate $500,000 from the Land Use Documents Fee Reserve to Downtown Precise Plan Comprehensive Update, Project 20-66, increasing the project budget from $2,582,000 to $3,082,000. (Five votes required)
2. Transfer and appropriate $300,000 from the Land Use Documents Fee Reserve to R3 Zoning District Update, Project 20-67, increasing the project budget from $1,897,000 to $2,197,000. (Five votes required)
3. Transfer and appropriate $150,000 from the Land Use Documents Fee Reserve to the 2023-2031 Housing Element, Project 21-58, increasing the project budget from $1,483,655 to $1,633,655. (Five votes required)
4. Transfer and appropriate $150,000 from the Land Use Documents Fee Reserve to Historic Preservation Ordinance Update, Project 22-45, increasing the project budget from $530,000 to $680,000. (Five votes required)
5. Transfer and appropriate $300,000 from the Land Use Documents Fee Reserve to Moffett Boulevard Precise Plan, Project 24-46, increasing the project budget from $1,510,000 to $1,810,000. (Five votes required)