Title
Shoreline Boulevard Transit Lane and Utility Improvements, Project 18-43-Amend Project Budget and Award Construction Contract
Recommended Action
1. Acting in its capacity as Board of Directors of the Shoreline Regional Park Community, transfer and appropriate $1,197,000 of Shoreline Regional Park Community 2018 Series A Bond Proceeds from Shoreline Boulevard at Highway 101 Bicycle/Pedestrian Bridge, Construction, Project 20-38, to the Shoreline Boulevard Transit Lane and Utility Improvements, Project 18-43.
2. Award the construction contract for the Shoreline Boulevard Transit Lane and Utility Improvements, Project 18-43, to Granite Rock Company for $14,518,586, and approve an additional construction contingency of $300,000 for a total not-to-exceed amount of $14,818,586.