File #: 204985   
Type: Consent Calendar Status: Agenda Ready
Meeting Body: City Council
On agenda: 4/22/2025
Title: Annual Water and Sewer Main Replacements, Projects 23-08 and 23-09-Various Actions
Attachments: 1. Council Report

Title

Annual Water and Sewer Main Replacements, Projects 23-08 and 23-09-Various Actions

Recommended Action

1.                     Find that in accordance with California Environmental Quality Act (CEQA) requirements, Annual Water and Sewer Main Replacements, Projects 23-08 and 23-09, is categorically exempt as Class 1, Existing Facilities, and on a separate and independent basis is exempt as Class 2, Replacement or Reconstruction, under CEQA Guidelines Sections 15301(b) and 15302(c), respectively.

 

2.                     Appropriate and transfer $1,501,000 from Annual Water Main Replacement, Project 24-08, to Annual Water Main Replacement, Project 23-08.  (Five votes required)

 

3.                     Appropriate and transfer $1,925,000 from Annual Sewer Main Replacement, Project 24-09, and $2,965,000 from the Wastewater Fund to Annual Sewer Main Replacement, Project 23-09.  (Five votes required)

 

4.                     Approve plans and specifications for Annual Water and Sewer Main Replacement, Projects 23-08 and 23-09, and authorize staff to advertise the project for bids.

 

5.                     Authorize the City Manager or designee to award the construction contract to the lowest responsive, responsible bidder if the low bid is within the available project budget of $10,938,000.