File #: 201846   
Type: Consent Calendar Status: Passed
Meeting Body: City Council
On agenda: 5/24/2022
Title: Shoreline Boulevard Interim Bus Lane and Utility Improvements, Projects 16-58 and 18-43-Various Actions
Attachments: 1. Council Report
Related files: 200658, 190673, 18630, 200224, 201410, 201322, 16-430, 16-641, 17-70, 18209, 190476

Title

Shoreline Boulevard Interim Bus Lane and Utility Improvements, Projects 16-58 and 18-43-Various Actions

Recommended Action

1.                     Authorize the City Manager or designee to pursue termination of the construction contract with Granite Rock Construction for Shoreline Boulevard Interim Bus Lane and Utility Improvements, Project 18-43.

 

2.                     Transfer and appropriate $259,331 from the Wastewater Fund and $238,000 from the Water Fund to Shoreline Boulevard Interim Bus Lane and Utility Improvements, Design, Project 16-58.  (Five votes required)

 

3.                     Acting in its capacity as Board of Directors of the Shoreline Regional Park Community, transfer and appropriate $80,000 from Shoreline Community Fund to Shoreline Boulevard Interim Bus Lane and Utility Improvements, Design, Project 16-58.

 

4.                     Authorize the City Manager or designee to amend the professional services agreement with Mark Thomas & Company, Inc., in the amount of $577,331 to provide additional design services in a not-to-exceed amount of $2,821,000.