Title
Northbound Shoreline Boulevard/U.S. 101 Off-Ramp Realignment, Design, Project 19-59-Transfer and Appropriate Funds, and Amend Professional Services Agreement
Recommended Action
1. Acting in its capacity as the Shoreline Regional Park Community Board, transfer and appropriate $385,000 from the Shoreline Community-North Bayshore Improvement Fee Subfund to Northbound Shoreline Boulevard/U.S. 101 Off-Ramp Realignment, Design, Project 19-59.
2. Authorize the City Manager or designee to amend the professional services agreement with AECOM Technical Services, Inc., for Northbound Shoreline Boulevard/U.S. 101 Off-Ramp Realignment, Design, Project 19-59, to add $350,000 for additional services, for a total agreement not-to-exceed amount of $2,215,000.