Title
Community Center Remodel, Project 17-32-Amend Project Budget and Award to the Low Bidder for the Second Phase Construction Project.
Recommended Action
1. Appropriate and transfer $2,200,000 from the Park Land Dedication Fund (as detailed in Attachment 1 to the Council report) to the Mountain View Community Center Remodel, Project 17-32, for a total project budget of $23,550,000. (Five votes required)
2. Award the construction contract for the Mountain View Community Center Remodel Second Phase to BHM Construction, Inc., for $16,793,664, which includes Additive Bid Alternates 1 and 4.b., and approve a construction contingency of $1,680,000.