Title: 2013-14 Concrete Sidewalk and Curb Repairs, Project 14-06, and Installation of ADA Curb Ramps, Phase VII, Project 12-24 - Approve Plans and Specifications/Authorize Bids.
Attachments: 1. Council Report, 2. ATT 1 - Sidewalk List, 3. ATT 2 - Curb Ramps List
Title
2013-14 Concrete Sidewalk and Curb Repairs, Project 14-06, and Installation of ADA Curb Ramps, Phase VII, Project 12-24 - Approve Plans and Specifications/Authorize Bids.
 
Recommended Action
1.      Authorize the transfer of $190,000 from 2012-13 Concrete Sidewalk and Curb Repairs, Project 13-06, to 2013-14 Concrete Sidewalk and Curb Repairs, Project 14-06.  (Five votes required)
 
2.      Approve plans and specifications for Installation of ADA Curb Ramps, Phase VII, Project 12-24, and 2013-14 Concrete Sidewalk and Curb Repairs, Project 14-06, and authorize staff to advertise the project for bid.
 