File #: 18173   
Type: Consent Calendar Status: Agenda Ready
Meeting Body: City Council
On agenda: 4/3/2018
Title: Citywide Trash Capture Phase I, Project 16-53-Various Actions.
Attachments: 1. Council Report
Related files: 200119

Title

Citywide Trash Capture Phase I, Project 16-53-Various Actions.

Recommended Action

1.                     Appropriate and transfer $250,000 from the Storm Drain Construction Fund to Citywide Trash Capture Device, Phase I, Project 16-53.  (Five votes required)

 

2.                     Authorize the City Manager to execute an amendment to the agreement with JMB Construction, Inc. for an additional construction contingency of $210,000 for a total contract amount of $1,587,020 in the Citywide Trash Capture Device, Phase I, Project 16-53.

 

3.                     Authorize the City Manager to execute a cost-sharing agreement with the Santa Clara Valley Water District (SCVWD) for installation of trash boom anchors at Permanente Creek.