Title: Storm Drain Master Plan Update, Project 16-54-Amend Design Professional Services Contract.
Attachments: 1. Council Report, 2. ATT 1 - Additional Services, Storm Drain Master Plan Memo

Title

Storm Drain Master Plan Update, Project 16-54-Amend Design Professional Services Contract.

Recommended Action

1.                     Appropriate and transfer $25,000 from the Construction/Conveyance Tax Fund to Storm Drain Master Plan Update, Project 16-54, increasing the project budget from $535,000 to $560,000.  (Five votes required).

 

2.                     Authorize the City Manager to amend the existing professional services agreement with Schaaf & Wheeler Consulting Civil Engineers of San Francisco for an additional $50,000 to provide civil engineering services for Storm Drain Master Plan Update, Project 16-54, resulting in a total not-to-exceed contract of $395,000.