File #: 190376   
Type: Consent Calendar Status: Agenda Ready
Meeting Body: City Council
On agenda: 6/4/2019
Title: Northbound Shoreline Boulevard/101 Off-Ramp Realignment Design, Project 19-59-Professional Services Agreement
Attachments: 1. Council Report, 2. ATT 1 - AECOM Scope of Work
Related files: 16-727, 17-192, 190313

Title

Northbound Shoreline Boulevard/101 Off-Ramp Realignment Design, Project 19-59-Professional Services Agreement

Recommended Action

Authorize the City Manager to amend a professional services agreement with AECOM of San Jose to prepare final plans, specifications, and estimates and bid documents and limited services during bidding and construction for the Northbound Shoreline Boulevard/101 Off-Ramp Realignment Design, Project 19-59, in the amount of $1,865,000.