Title
Shoreline Park Water Control Structures Improvements, Project 23-44-Various Actions
Recommended Action
Acting in its capacity as the Board of Directors for the Shoreline Regional Park Community:
1. Approve plans and specifications for Shoreline Park Water Control Structures Improvements, Project 23-44, Package 1, and authorize staff to advertise the project for bids.
2. Authorize the Community Manager or designee to award a construction contract for Shoreline Park Water Control Structures Improvements, Project 23-44, Package 1, to the lowest responsible responsive bidder if the low bid is within the available project budget.
3. Find that, in accordance with California Environmental Quality Act requirements, Shoreline Park Water Control Structures Improvements, Project 23-44, Package 1, is categorically exempt. Within Package 1, the replacement of the Coast-Casey Pump Station sump pump pipe is categorically exempt as Class 1, Existing Facilities, and on a separate and independent basis, Class 2, Replacement or Reconstruction, under California Public Resources Code, Section 15301 and Section 15302. The demolition and removal of the boardwalk, repair of the spillway outlet structure slide gate, and Sailing Lake outlet structure are categorically exempt as Class 1, Existing Facilities, under California Public Resources Code Section 15301.
4. Direct staff to complete environmental clearance, permitting, and plans and specifications to restore Sailing Lake Habitat Island as part of Shoreline Park Water Control Structures Improvements, Project 23-44, Package 3, with Restoration Alternative 2, Repair Eroded Slopes and Expand Island Size, and Barrier Improvement Alternative C, Drilled Wooden Piles.