File #: 204485   
Type: Consent Calendar Status: Agenda Ready
Meeting Body: City Council
On agenda: 10/22/2024
Title: MV Community Shuttle EV Charging Units, Project 22-44-Various Actions
Attachments: 1. Council Report

Title

MV Community Shuttle EV Charging Units, Project 22-44-Various Actions

Recommended Action

1.                     Find that in accordance with the California Environmental Quality Act (CEQA) requirements, MV Community Shuttle EV Charging Units, Project 22-44, is categorically exempt as Class 4, Minor Alterations to Land, under CEQA Guidelines Section 15304.

 

2.                     Transfer and appropriate $190,000 of General Fund Reserve funding and $12,000 of Construction/Conveyance Tax funding from Annual New Energy Conservation Measures, Project 19-25, to MV Community Shuttle EV Charging Units, Project 22-44.  (Five votes required)

 

3.                     Transfer and appropriate $25,000 of Construction/Conveyance Tax funding from Annual New Energy Conservation Measures, Project 23-14, to MV Community Shuttle EV Charging Units, Project 22-44.  (Five votes required)

 

4.                     Transfer and appropriate $325,000 from the Construction/Conveyance Tax Fund to MV Community Shuttle EV Charging Units, Project 22-44.  (Five votes required)

 

5.                     Approve plans and specifications for MV Community Shuttle EV Charging Units, Project 22-44, and authorize staff to advertise the project for bids.

 

6.                     Authorize the City Manager or designee to award a construction contract to the lowest responsive responsible bidder if the bid is within the total project budget of $1,186,798.